As Cabinet Member for Highways and Transport, I agree to approve the progression and delivery of the A226 Galley Hill scheme through to completion and specifically:
i. Confirm that the decisions contained within Record of Decision 26/00019 remain extant.
ii. Subject to a successful Structures Fund bid and satisfactory review of the grant terms and conditions, approve the acceptance of £40.8m from the Department for Transport Structures Fund and the associated £4.5m match funding, comprising £3m from KCC and £1.5m from Ebbsfleet Development Corporation
iii. Subject to the award and acceptance of the Structures Fund and confirmation of the associated match funding approve the progression and delivery of the A226 Galley Hill scheme through to completion, including:
a. acquisition of the necessary land and rights, by voluntary agreement or through the promotion and implementation of a Compulsory Purchase Order where required;
b. progression of all necessary statutory approvals and consents; and
c. procurement and award of the contracts required to deliver the scheme, subject to the Council’s relevant internal procurement and governance requirements.
iv. Delegate authority to the Director of Infrastructure, in consultation with the Corporate Director of Growth, Environment and Transport, to approve and enter into all contracts, agreements and other legal documentation necessary to secure the land and property interests required for delivery of the scheme.
v. Delegate authority to the Corporate Director of Growth, Environment and Transport to take the actions necessary to implement and complete the A226 Galley Hill scheme within the approved funding envelope, including, but not limited to:
a. in consultation with the Corporate Director of Finance, finalising and accepting the Structures Fund and entering into any associated funding agreements;
b. entering into contracts, agreements and other legal documentation necessary for the delivery and completion of the scheme;
c. in consultation with the Cabinet Member for Highways and Transport, agree non-material changes to the scheme required during its delivery; and
d. taking any other actions necessary to give effect to this decision.