Issue - meetings

20/00028 - A20 London Road Aylesford Junction Improvement

Meeting: 17/07/2020 - Environment & Transport Cabinet Committee (Item 264)

264 20/00028 - A20 London Road Aylesford Junction Improvement pdf icon PDF 791 KB

Additional documents:

Minutes:

Russell Boorman (Senior Major Capital Programme Project Manager) was in attendance for this item.

 

1.    Mr Payne (Cabinet Member for Highways and Transport) and Mr Boorman introduced the report which set out information about the A20 London Road Aylesford Junction Improvement Scheme and sought the committee’s approval to progress to the next stages of development and delivery, including authority to progress statutory approvals and to enter into funding, land and construction contracts.

 

2.    It was RESOLVED that the proposed decision (20/00028), to be taken by the Cabinet Member for Highways and Transport, to:

 

(a)       give approval to the outline design scheme for the A20 London Road Aylesford in Tonbridge & Malling for development control and land charge disclosures, drawing number A20HR-CAP-HGN-00-DR-C-0043,

 

(b)      give approval to progress all statutory approvals or consents required for the scheme, drawing number A20HR-CAP-HGN-00-DR-C-0043,

 

(c)       give approval to enter into land agreements with third parties as necessary,

 

(d)      give approval to enter into construction contracts as necessary for the delivery of the scheme,

 

(e)      give approval to undertake engagement with all relevant stakeholders as identified in the communication plan; and

 

(f)        give approval for the Corporate Director for Growth, Environment & Transport, under the Officer Scheme of Delegations and in consultation with the Corporate Director for Finance and Procurement, to enter into relevant legal agreements and take other actions necessary to implement this decision,

 

be endorsed.