Neil Clarke, Flood Risk Project Manager was in attendance for this item
1) Mr Hills outlined the report.
2) Further to questions from Members, it was noted that:
· It was important to consider what was best practice nationally when looking at what was happening in the South East.
· Direct discharge to ground water was not allowed. A minimum of 1 metre of clear ground between the point of infiltration to ground water, if it was clean run off. Distance for removing pollution was bigger.
· There had been flooding as the dyke system had not been sufficient to manage heavy rainfall.
· There were some issues with salinity in the dyke system and it was complicated keeping the balance.
3) The Committee endorsed the report as the basis for a lobbying document to the Southern Regional Flood and Coastal Committee for investment funding in Romney Marsh.