Tim Read (Interim Director of Highways,
Transportation and Waste) and Richard Shelton (Major Capital
Programme Project Manager) were in attendance for this
item.
- Mr Whiting
(Cabinet Member for Planning, Highways, Transport and Waste)
introduced the report which sought the Committee’s approval
to endorse the preferred outline design of the Sturry Link Road
which would run north and west of the A28 and A291. He welcomed
Members questions and comments which would be used to inform the
final decision.
- Mr Shelton
said that the Highway Authority had identified congestion issues
within the town centre of Sturry; the Link Road would allow all
A28/A291 through traffic to avoid the Sturry level crossing and
therefore reduce the amount of congestion. Furthermore, in July
2017, Canterbury City Council’s Local District Plan had
identified land at Sturry and Broad Oak as a suitable location for
a new housing development. This required improved infrastructure,
including a Sturry Link Road to relieve the level crossing, road
investiture to the new housing and access to the station. The
proposal was most recently presented to the Environment and
Transport Cabinet Committee in July 2017 which identified the need
to go out to public consultation. A public consultation exercise
was undertaken for six weeks from 26 July 2017 to 6 September 2017
and following the feedback received, amendments were made to the
scheme which included: the widening of shared-use footway and cycle
paths, the widening of the existing Shallock Road due to safety
concerns of Network Rail, additional signal-controlled crossings,
the relocation of a surface water pond; and discussions had taken
place with bus operators regarding the location of bus stops. The
next stage of the process would be for the Cabinet Member to
approve the preferred scheme which would then be submitted as a
planning application to the County Council. Mr Shelton assured the
Committee that the scheme had been developed by Kent County Council
in conjunction with Canterbury City Council, Network Rail and the
Environment Agency to achieve the best possible outcome for the
Sturry area within the restraints of the allocated
funding.
- In response
to concerns regarding the development timetable, Mr Shelton said
that the developer for the Sturry site had submitted a planning
application in August 2017 which went out to consultation. Work had
commenced to review the responses from that consultation and to
amend the design proposals where feasible and a re-submission of
that planning application was due to take place in four to six
weeks’ time. These would then need to go through a formal
planning process. Kent County Council needed to ensure that the
application for the Sturry Link Road was submitted to support the
applications for the housing developments. Mr Shelton advised the
Committee that should the scheme be successful in getting consent
to progress, the housing development would start to be built in
2019 and the Sturry Link Road would commence 2020/2021.
- With regard
to the level crossing and the impact this would have on journey
time, Mr Shelton said that the system was operated and managed by
Network Rail and whilst there would be significant improvements,
the Highways Authority would not be able to provide exact
figures.
- In response
to comments regarding the need for a traffic-signal controlled
roundabout to support the traffic flow during peak times, Mr
Shelton said that the traffic modelling that had been undertaken
suggested that, the roundabouts as currently sized, would
facilitate the traffic moving both east and west and this would act
as a break in the traffic for those vehicles going south onto the
A291. Mr Shelton agreed to review the query further against the
current traffic modelling and circulate the information to Members
of the Committee.
- Members
commented on the environmental damage of the scheme and asked
whether the UK would move towards a European approach to removing
asphalt roads by replacing them with more cycle paths and safer
walking routes. Mr Read informed the Committee that due to the
deregulated market in which the UK exists, Kent County Council
needed to bid for Government funding when available. The funding
that was awarded for the development of the A28/A291 Sturry Link
Road was allocated specifically for the development of the
infrastructure needed to meet the immediate demand. He said that
65% of those who responded to the public consultation agreed with
the principle of the scheme and appreciated the environmental
impact it would have. In addition, Mr Shelton assured Members that
that cycle paths and footways were provided within the scheme along
with off-route cycle ways.
- Mr Read said
that in terms of justifying the money received from Government,
officers undertook a review of the business case to look at the
benefits of building a dual carriageway against the potential cost
of building a dual carriageway. The outcome of the review revealed
that the funding would not support the desired infrastructure and
therefore the scheme presented to the Committee contained the
alternative modelling which could be achieved.
- Mr Shelton
confirmed that the junction at Sturry Crossing at the A28/A291 was
designed to be a traffic signal-controlled junction.
- In response
to Members requests for further examination of the details within
the scheme, Mr Read agreed to prepare for the Cabinet Member for
Planning, Highways Transport and Waste, a detailed analysis of the
cost involved to build an extra lane, the benefit this would have
and a review of the viaduct in order to achieve the correct balance
between cyclists, pedestrians and buses, to ensure that an informed
decision around the infrastructure could be made.
- Mr Whiting
acknowledged the comments made by Members of the Committee and
agreed to receive further information from the officers regarding
the cost benefits of the Members proposals.
- Prior to the
conclusion of the discussion Mr Cook proposed, and Mr Love seconded
that a change be made to the recommendation in the report to add at
the end of the words ‘proposed decisions’ the
additional phrasing as follows:
‘subject to the Cabinet Member giving further
consideration to the detailed points raised during the Committee
regarding the roundabout at Sturry Hill and the capacity of the
viaduct’
This was generally accepted by the
Committee.
-
RESOLVED that subject to the Cabinet Member giving
further consideration to the detailed points raised during the
Committee regarding the roundabout at Sturry Hill and the capacity
of the viaduct, the decision proposed to be taken by the Cabinet
Member to:
i) give approval to the
revised preferred outline design scheme for the Sturry Link Road
Drawing No. 430392/000/71 Rev 0 – Fig 2, updated to
incorporate amendments arising from the public consultation, for
development control and land charge disclosures.
ii) give approval to all acts required to acquire
the land and rights for the carrying out and completion of the
A28/A291Sturry Link Road scheme, including by means of a compulsory
purchase order, and any other necessary statutory
orders.
iii) accept, if necessary, any blight notice that
may be served, on terms to be agreed with the Director of
Infrastructure, Strategic and Corporate Services; and
iv) delegate to the Corporate Director of Growth,
Environment & Transport, under the Officer Scheme of
Delegations, to take further or other decisions as may be
appropriate to deliver the A28/A291 Sturry Link Road scheme in
accordance with these recommendations and the earlier overarching
decisions given under Record of Decisions
15/00070A and 17/00061, that remain extant.
be endorsed.
Mr M
Whybrow, and Mr B Lewis asked
that their votes against the
recommendation be minuted.