Issue - decisions

18/00034 - Herne Relief Road - Bullockstone Road Improvement Scheme

19/07/2018 - 18/00034 - Herne Relief Road - Bullockstone Road Improvement Scheme

As Cabinet Member for Planning, Highways, Transport and Waste, I agree to:

 

  • the feasibility design for the Herne Relief Road, Bullockstone Road Improvements for development to full design, development control and land disclosures shown in principal on drg no. 4300400/000/09.
  • progress the design through the next stages of development and delivery including any ancillary works such as drainage and environmental mitigation;
  • take all steps necessary to obtain and implement all statutory Orders and approvals or consents required for the schemes;
  • all acts required to acquire the land and rights for the carrying out and completion of the Bullockstone Road Improvements, including by means of a compulsory purchase order;
  • enter into firm land and funding agreements associated with development contributions;
  • enter into construction contracts as necessary for the delivery of the scheme subject to the approval of the Procurement Board to the recommended procurement strategy,
  • seek amendments to the existing planning permission as required, during the next stages of the scheme design, and
  • the Corporate Director of Growth, Environment & Transport, under the Officer Scheme of Delegations, to take further or other decisions as may be appropriate to deliver the Bullockstone Road Improvement Scheme in accordance with these recommendations