As Cabinet Member for Education and Skills I:
i. Agree to increase the funding allocated to expand Borden Grammar School from £6,975,000 to £8,950,282 through providing an additional £1,975,282 from the Basic Need capital budget.
ii. Authorise the Director of Infrastructure in consultation with the General Counsel and Director of Education to enter into any necessary contracts / agreements on behalf of the County Council.
iii. Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts. Variations to contract value to be no more than 10% above the capital funding agreed by the Cabinet Member without requiring a new Record of Decision.