Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Proposal to agree to proceed with the
Tonbridge High Street Regeneration scheme delivery during 2015/16
and 2016/17
Decision:
As
Cabinet Member for Transport & Environment, I give approval to
take 7 Local Growth Fund schemes through the next stages of
development and delivery including authority to progress statutory
approvals and consultation where appropriate, and to enter into
funding and construction contracts.
These schemes are:
-
Tonbridge Town Centre Regeneration Scheme, in
drg. No. 4300127/000/11,
-
North Deal Transport Improvements, in drg. No. NDTI-1,
-
Maidstone Sustainable access to Employment areas, as
shown in drg. No. MSAEA-1,
-
Sittingbourne Town Centre Regeneration, as shown in
drg. No. STCR-1,
-
A26 London Rd/Speldhurst
Rd/Yew Tree Rd, Tunbridge Wells, in drg. No. KCC/LTP/YTR/001,
-
West Kent Local Sustainable Transport Fund
and
-
Kent Thameside Local
Sustainable Transport Fund.
Specifically I:
-
give approval to progress the design of the schemes
for development control and land charge disclosures;
-
give approval to progress all statutory approvals or
consents required for the schemes;
-
give approval to carry out consultation on the
schemes including Equalities Impact
Appraisals;
-
give approval to enter into Single Local Growth Fund
funding agreement subject to the approval of the Corporate Director
of Finance & Procurement, and
-
give approval to enter into construction contracts as necessary for
the delivery of the schemes subject to the approval of the
Procurement Board to the recommended procurement
strategy.