Decision details

Proposed expansion of Iwade Primary School, Sittingbourne

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The Swale section of the Kent Commissioning Plan for Education Provision 2013-18 has identified a need for up 87additional Reception Year places within Swale district.

The expansion of Iwade Community Primary School will help to address these pressures and adheres to the principles of our Commissioning Plan as it increases capacity at a good, popular school.

Financial Implications:

It is proposed to enlarge Iwade Community Primary School by 210 places taking the PAN to 90 (3FE) for the September 2015 intake and eventually a total capacity of 630 places.

a.         Capital - The enlargement of the school requires the provision of 7 additional classrooms, as well as ancillary facilities.  A feasibility study has been completed. The total cost is estimated to be in the region of £3,500,000 of which £1,946,501 will be funded from Targeted Basic Need and the remainder from the Basic Need Budget. The costs of the project are estimates and these may increase as the project is developed.  If the cost of the project is greater than 10% the Cabinet Member will be required to take a further decision to allocate the additional funding.

b.        Revenue - The school will receive increased funding through the Delegated Budget on a 'per pupil' basis.

c.        Human - Iwade Community Primary School will appoint additional teachers, as the school size increases and the need arises.

Decision:

The Cabinet Member for Education and Health Reform has taken the decision to:

(i)              Issue a public notice to expand Iwade Community Primary School, by 210 places from 2FE (60) to 3FE (90).

 

And, subject to no objections being received to the public notice

 

(ii)             Expand the school

(iii)            Allocate £3,500,000 from the Education. Learning and Skills Capital Budget.

(iv)           AUTHORISE the Director of Property and Infrastructure Support in consultation with the Director of Law and Governance to enter into any necessary contracts/ agreements on behalf of the County Council

(v)             AUTHORISE the Director of Property and Infrastructure Support to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts

(vi)           Should objections, not already considered by the Cabinet Member when taking this decision, be received during the notice period a separate decision will be required in order to continue the proposal and expand the school to allow for proper consideration of the points raised.  This decision is subject to planning permission being granted.

Publication date: 24/02/2014

Date of decision: 24/02/2014

Effective from: 04/03/2014