As Cabinet Member
for Highways and Transport, I give approval for the county council
to:
-
proceed with the currently developed route and design for North
Thanet Link and for this to be further developed as a preferred
option which best meets the objectives of the scheme.
-
enable KCC officers to project manage, input into the delivery and
supervision of the project, with the cost of all staff and
consultant time being recoverable against the project funding.
-
progress the preferred option through the next stages of scheme
development including detailed design, associated site
surveys/investigations, and ancillary works relating to drainage,
environmental and highway mitigation.
-
develop and submit a planning application for the scheme, following
completion of the outline design process.
-
take all steps necessary to obtain and implement all Statutory
Orders and approvals or consents required for the scheme, including
but not limited to Compulsory Purchase Order, Side Roads Order and
any Traffic Regulation Orders required for the delivery and
successful operation of the scheme.
-
negotiate and complete all required land acquisition including by
means of Compulsory Purchase Order as necessary to secure the
delivery and future maintenance of the scheme.
-
enter into Major Road Network funding agreement with the Department
for Transport, subject to the approval of the Corporate Director
for Finance and for any secured funding to be spent on the design,
development and delivery of the
scheme.
-
progress and complete a procurement process and enter into construction contracts as necessary for
the delivery of the scheme, subject to the approval of Strategic
Commissioning.
-
allow the Corporate Director of Growth, Environment and Transport,
under the Officer Scheme of Delegations, to take further or other
decisions as may be appropriate to deliver the North Thanet Link
scheme in accordance with these recommendations.