As Cabinet Member for Environment, I agree to:
APPROVE the procurement and contract award of a N+P via the CSKL Framework for the receipt and processing of dry mixed recyclables for an initial period of 24 months, with up to a further 36 months extension period.
DELEGATE authority to the Director of Environment and Circular Economy, to take relevant actions to facilitate the required procurement activity;
DELEGATE authority to the Director of Highways and Transportation, in consultation with the Cabinet Member for Environment to take relevant actions, including but not limited to, awarding, finalising the terms of and entering into the relevant contracts or other legal agreements, as necessary, to implement the decision; and
DELEGATE authority to the Director of Environment and Circular Economy in consultation with the Cabinet Member for Environment to award extensions of the contract in accordance with the extension clauses within the contract (up to 36 months).