As Cabinet Member for Highways and Transport, I agree to:
i. Approve the delivery of a traffic calming scheme to mitigate the impact of traffic arising from the Kings Hill Phase 3 development.
ii. Approve that the cost of staff and consultant time to project manage, input into the delivery and supervision of the scheme, be recoverable against the S106 Developer Contributions and Kent Lane Rental funding.
iii. Approve to progress all statutory approvals or consents required for the scheme.
iv. Approve the implementation of permanent Traffic Regulation Orders, if required as such associated with any speed limit reductions, subject to completing the statutory consultation process associated with Traffic Regulation Orders.
v. Approve any additional consultation/engagement as required for the scheme.
vi. Approve to enter into construction contracts as necessary for the delivery of the scheme subject to a review of the procurement strategy by the Strategic Commissioning team; and
vii. Delegate authority to the Corporate Director of Growth, Environment and Transport in consultation with the Cabinet Member for Highways and Transport to take relevant actions, including but not limited to finalising the terms of and entering into required contracts or other legal agreements, as necessary to implement the decision.