Issue - decisions
25/00036 - Expansion of Sir Geoffrey Leigh Academy, Green Street Green Rd, Dartford DA1 1RB, by 2 FE, increasing the Published Admission Number (PAN) from 240 places per year group to 300 places per year group
As Cabinet Member for Education and Skills, I
agree to:
- ALLOCATE £9,298,049 from the
CYPE Capital Budget to complete the permanent expansion of Sir
Geoffrey Leigh Academy, bringing the total project budget to
£10,698,049.
- DELEGATE authority to the Director
of Infrastructure to, in consultation with the Director of
Education, enter into any necessary contracts or other legal
agreements, as required to implement this decision; and
- AGREE for the Director of
Infrastructure to be the nominated Authority Representative within
the relevant agreements, with authority to enter variations as
envisaged under the contracts.