This is a default template, your custom branding appears to be missing.
The custom branding should be at https://www.kent.gov.uk/_designs/moderngov/template if you cannot load this page please contact your IT.

Technical Error: Error: The request was aborted: Could not create SSL/TLS secure channel.

  • Issue
  • Issue details

    19/00043 - Basic Need Programme Update and Proposed Process for School Organisation Proposals

    Background

     

    The Cabinet member for Children, Young People and Education will propose a new process to  ensure key decisions would be made at a time when robust information is available.  This includes costs, deliverability, and timescales in addition to the greater understanding of risk associated with each scheme. Any potential reputational risks to KCC should reduce. Implementation dates can be set with greater certainty, reducing situations where the school and KCC are required to admit pupils ahead of the buildings being available.  Importantly schemes which become poor value for money due to high abnormal costs can be reconsidered before KCC is legally committed via a public notice.

     

    The current CYPE Basic Need Programme consists of 79 projects across primary, secondary and special schools ranging from bulge years and expansions through to completely new schools. The current total value of the programme is £302.1m over the period 2018-2021.

     

    The programme has, over the past seven years, been managed such that any cost pressures have been contained within the budget approved by County Council. In order to manage this budget effectively a programme management approach has been adopted which involves CYPE, Infrastructure and GEN2.  The present approval process for capital projects can lead to budgets being set at a stage when full cost details are unavailable.  This can create a situation where some schemes are delivered at a lower cost than originally anticipated, some are withdrawn for a variety of reasons, and others become more expensive as design and planning stages proceed.

     

    Currently, using the mandate of the approved KCP, officers move individual school organisation proposals forward. Initial feasibility work is carried out to move from an identified pressure, i.e. 1FE within a particular planning area to a proposed solution.  Depending upon the point in the annual cycle that this information becomes available, the next iteration of the KCP may name the intended scheme.  The proposal next moves to public consultation.  This is led by KCC if it relates to a maintained school, or by the trust if an academy or free school.  The outcome of consultations, together with estimated capital costs derived from the initial feasibility study, are reported to CYPE Cabinet Committee.  The Cabinet Committee’s views on the proposal are then considered by the Cabinet Member for CYPE, who decides whether to progress the scheme.  In the case of maintained schools this results in a statutory public consultation being issued in the form of a public notice, and in the case of an academy/free school, a decision to make the capital funds available, subject to any decision needed from the Secretary of State.  It is this part of the process we recommend is amended.

     

    The current arrangements result in a decision being made, and public notice issued, based on a high-level budget estimate and an early assessment of timescales for delivery.  When the statutory public notice is issued, a “complete proposal” is also produced and published in line with the requirements of Regulations.  This sets out the County Council’s commitment to make the funding available to deliver the scheme, and sets the implementation date.  The risks of a scheme running over-budget and over-time are significantly greater at this point, than if the key decision was made later in the process. 

     

    Implementing a revised decision-making process,  will ensure that key decisions are made at a time when robust information is available.  This includes costs, deliverability, and timescales in addition to the greater understanding of risk associated with each scheme. Any potential reputational risks to KCC should reduce. Implementation dates can be set with greater certainty, reducing situations where the school and KCC are required to admit pupils ahead of the buildings being available.  Importantly schemes which become poor value for money due to high abnormal costs can be reconsidered before KCC is legally committed via a public notice.

     

    The reasons for needing to adjust the budget allocations for the schemes above will be reported to CYPE Cabinet Committee, and these have been taken in to account in the final decision.

    Decision type: Key

    Reason Key: Expenditure or savings of more than £1m;

    Decision status: Recommendations Approved

    Division affected: Ashford Rural West; Ashford South; Dartford North East; Gravesend East; Maidstone Rural East; Sevenoaks North & Darent Valley; Sevenoaks Town; Swanscombe and Greenhithe; Tonbridge; Tunbridge Wells South; Tunbridge Wells West;

    Notice of proposed decision first published: 24/04/2019

    Decision due: Not before 3rd Jun 2019 by Cabinet Member for Children, Young People and Education
    Reason: In order that the proposed decision can be publsihed for a minimum of 28 days, in accordance with statutory requirements

    Lead member: Cabinet Member for Children, Young People and Education

    Lead director: Keith Abbott

    Department: Education & Young People's Services

    Contact: David Adams, Assistant Director Education (South Kent) 03000 414989 Email: david.adams@kent.gov.uk Tel: 01233 898559.

    Consultees

    The proposed decision was considered by the Children’s, Young People and Education Cabinet Committee on 7 May 2019.

    Financial implications: The basic need programme has, over the past seven years been managed such that any cost variations have been contained within the budget approved by County Council. In order to manage this budget effectively, a programme management approach has been adopted by GEN2/Infrastructure in liaison with CYPE. This approach has enabled the £17.12M of pressure generated by the increasing costs of the schemes identified above to be contained within existing programme budget. Some of the potential additional costs identified may prove to be revenue rather than capital in nature. If these costs materialise and prove to be revenue rather capital then work will be undertaken to manage this.

    Legal implications: The Local Authority as Strategic Commissioner of Education Provision has a key role in securing funding to provide sufficient education provision in the County, particularly in schools.

    Equalities implications: The proposal to change the sequencing of the decision-making process for school organisation proposals does not present any equalities issues. Equality Impact Assessments were completed for each scheme at the time of the original decisions. It is not envisaged that any changes would be required as a result of the proposals to vary the individual Record of Decisions.

    Decisions

    Agenda items