Issue details

20/00034 - Procurement of Temporary Body Storage Facilities

Background:

 

On 12 January 2020, it was announced that a new coronavirus had been identified. COVID-19 is highly contagious and the World Health Organisation has declared the risk and spread of the disease as a pandemic with Europe now at its epicentre. Although the Government has taken action to control the spread and rate of infection, there is expected to be a higher number of deaths resulting from the disease, than would ordinarily be experienced from other causes.

 

To enable the initial phase of the provision to be secured an urgent order has been placed with a supplier using officer delegations.  It is likely that further decisions will be taken in the coming days, week to ensure that arrangements are in place to meet the national need. The financial commitment associated with this is likely to exceed £1million and would ordinarily be a key decision. 

 

Reason for Urgency:

 

Kent is not alone in the need to make appropriate preparations for increased mortuary demand and supplies of the relevant equipment, land and ancillaries are limited.  It is therefore crucial that KCC takes necessary steps to secure the additional capacity immediately while it is still available.  Failure to take immediate action could limit KCC’s ability to meet its statutory obligations to provide sufficient mortuary capacity.

 

This key decision is now required urgently to ensure appropriate authority is in place to support ongoing retention and use of the additional capacity which has already been identified and to provide necessary flexibility to allow for swift significant Officer decisions on this project should further capacity and facilities be required in response to the fast-moving situation. Should additional facilities be required, officers will inform the Leader in writing at the time.

 

Options:

 

Current mortuary capacity in Kent and Medway is insufficient to deal with the Government’s forecast number of excess deaths from COVID-19, therefore additional space needs to be procured efficiently to respond to  modelling by the Government as the understanding of the virus’ epidemiology continues to evolve

 

 

Additional Financial information:

 

The total budget allocation to facilitate the project is £11m. This will cover the costs for an initial facility and for additional capacity if required. Whilst the expenditure incurred as a result of this decision will initially be funded by the Council, the Government has confirmed that councils will be reimbursed for costs incurred as part of the response to the Covid 19 outbreak.  The expenditure being incurred is to support a storage facility capable of managing the number of bodies in line with the forecast data provided by Government. 

Costs for the set-up of the initial facility total £973,428.15 and are listed below;

·         Erection of hoarding on site to maintain site security and privacy - £76,736.00.

·         Set up and hire costs from Fews Marquees;

o   13th April 2020 to 10th May 2020 - £403,510.00

o   11th May 2020 to 7th June 2020 - £116,120.00

o   Additional hire to meet minimum 20 week hire period - £116,120.00 x 3

·         Repairs and maintenance to B Block to make safe for use (including roof repairs) – £28,702.15.

 

As the full provision is put in place additional costs will be incurred for the set-up and operation of the site.

 

The costs of the further facilities is unknown but will be considered by officers in line with delegated powers before making any decisions.

 

Due to the urgency KCC is invoking Section 32 of the Public Contracts Regulations 2015. This provides for the use of a single source supplier without the need to go out to public competition. This approach is consistent with the advice from the Cabinet Office.

 

Decision type: Key

Reason Key: Expenditure or savings of more than £1m;

Decision status: Recommendations Approved

Division affected: (All Division);

Notice of proposed decision first published: 06/04/2020

This decision will be taken under urgency procedures.

Reason for urgency:
Kent is not alone in the need to make appropriate preparations for increased mortuary demand and supplies of the relevant equipment, land and ancillaries are limited. It is therefore crucial that KCC takes necessary steps to secure the additional capacity immediately while it is still available. Failure to take immediate action could limit KCC’s ability to meet its statutory obligations to provide sufficient mortuary capacity.

This key decision is now required urgently to ensure appropriate authority is in place to support ongoing retention and use of the additional capacity which has already been identified and to provide necessary flexibility to allow for swift significant Officer decisions on this project should further capacity and facilities be required in response to the fast-moving situation. Should additional facilities be required, officers will inform the Leader in writing at the time.

Decision due: 6 Apr 2020 by Leader of the Council
Reason: Urgent Decision taken under statutory urgency provisions

Lead member: Leader of the Council

Lead director: Barbara Cooper

Department: Growth, Environment & Transport

Contact: Rebecca Spore, Director of Infrastructure Email: rebecca.spore@kent.gov.uk Tel: 01622 221151.

Consultation process

Any decisions taken to procure further body storage provision will be taken in active response to the fast paced and uncertain evolution of the COVID-19 pandemic, and therefore no public consultation is planned or already undertaken.

 

Consultees

This decision is being taken under urgency procedures. Notice of the decision will be shared with the Chair of Scrutiny, Group spoke persons of the Scrutiny Committee, Chair and Group Spokespersons of the Growth, Economic Development and Communities Cabinet Committee

Financial implications: The total budget allocation to facilitate the project is £11m. This will cover the costs for an initial facility and for additional capacity if required. Whilst the expenditure incurred as a result of this decision will initially be funded by the Council, the Government has confirmed that councils will be reimbursed for costs incurred as part of the response to the Covid 19 outbreak. The expenditure being incurred is to support a storage facility capable of managing the number of bodies in line with the forecast data provided by Government.

Legal implications: KCC has an obligation under the Civil Contingency Act 2004 to take the lead in responding to humanitarian impacts that result from an emergency that straddles more than one District within the county.

Equalities implications: See EqIA for details

Decisions