Issue details

25/00086 - Proposal to facilitate the expansion of Parkwood Hall Co-operative Academy, Beechenlea Lane, Swanley, Kent, BR8 8DR

Proposed decision –The Cabinet Member for Education and Skills:

 

  1. APPROVE the requisite funding from the Children Young People and Education High Needs Capital Programme that will be required to increase Parkwood Hall Co-operative Academy’s designated number from 120 to 192 students

 

  1. DELEGATE authority to the Director of Infrastructure, in consultation with the Head of Law and Director of Education to enter into any necessary contracts or other legal agreements as required to implement the decision; and

 

  1. AGREE for the Director of Infrastructure, to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts.

 

Reason for the decision

 

Kent County Council (KCC) as a Local Authority, has a statutory duty to ensure sufficient high quality school places are available, in the right places for all learners, while at the same time fulfilling our other responsibilities to raise education standards and promote parental preference. The Kent Commissioning Plan 2025-2029 indicated that there will be a shortfall in Special School provision in North Kent. Even though KCC’s direction of travel is to increase Special Educational Needs (SEN) provision in mainstream schools and associated Specialist Resource Provisions (SRPs), due to already identified shortfalls and anticipated population growth in certain areas of North Kent, more specialist provision is required for children and young people with more complex needs.

 

KCC SEN Data for North Kent as at April 2025, evidenced that there were 237 children and young people waiting for a Special School placement, and 243 open cases, of which was anticipated that a large number would require a Special School placement.

 

In July 2023 KCC was informed that it had been successful in bidding for a new 250 place Profound, Severe, and Complex Needs (PSCN) Special School in North Kent (Swanley). The school had an initial target opening date of September 2026 and was to be funded and built by the Department for Education (DfE). However, for a number of reasons progress has been incredibly slow and there are now concerns that the school may not progress any further. Even if it were to continue, that school would not be built until 2028 at the very earliest and as the data shows, provision is required now. KCC Officers and the Cabinet Member for Education and Skills continue to push the DfE and Ministers for confirmation of the status of the proposed new Swanley Special School.

 

The proposal to facilitate the expansion of Parkwood Hall Co-operative Academy will create 48 places of additional primary provision (Reception to Year 6) plus additional places for secondary aged pupils. The building project for this expansion will be managed by Parkwood Hall Co-operative Academy, while KCC Infrastructure will oversee the scheme from a quality assurance perspective.

 

If no further action is taken in the longer term, KCC will find it extremely difficult to provide sufficient state-funded Special School provision in North Kent.

 

Background – Provide brief additional context

 

Parkwood Hall Co-operative Academy is a Single Academy Trust and officially sits under the

Royal Borough of Kensington and Chelsea (RBKC) but is located in Swanley Kent. KCC is the

main placing authority with the school. Parkwood HallCo-operative Academy is a Special

School for children and people aged 8-19 (Year 4 to Year 14) who have moderate to severe

learning difficulties and Autism. Many of the students have additional needs including ADHD,

Downs Syndrome and language difficulties. All students have Education, Health and Care

Plans. Following an inspection that took place in July 2025, Ofsted deemed Parkwood Hall Co-

operative Academy to be a ‘GOOD’ in 4 out of the 5 areas, and ‘OUTSTANDING’ in the area of

Behaviours an Attitudes.

 

The Principal of Parkwood Hall Co-operative Academy is already admitting students over and

above the designated number. Currently the number of students on roll is 135. Parkwood Hall Co-operative Academy continues to admit students with more complex needs, whilst ensuring the quality of education for all students is maintained.

 

Due to the school’s location RBKC now has limited interaction with the school and places a

very limited number of children and young people there. KCC continues to be one of the main

placing authorities with Parkwood Hall Co-operative Academy, placing 61 students out of a total school roll of 136 for the 2024/2025 academic year. For the start of this current academic year, 2025/2026, the school has 65 students placed by Kent out of a total school roll of 135 with no students placed from RBKC.

                       

KCC has formed strong working relationships with the Senior Leadership of Parkwood Hall Co-

operative Academy, and the school has indicated its very clear desire to be recognised as part

of the Special Educational Needs (SEN) system in Kent. Parkwood Hall Co-operative Academy

has acknowledged the need for more specialist placements for children with complex needs

predominantly across the primary age groups, and has therefore proposed to expand its age

range from what is currently 8- to 19-year-olds (Year 4 to Year 14) to 4-to-19-year olds

(Reception to Year 14) to support need in the North Kent area.

 

North Kent is still encountering significant growth primarily in Dartford, but the other two districts

of Gravesham and Sevenoaks are fast approaching completion of their new Local Plans, which

will see significant housebuilding required for the period up to 2040 and beyond.

 

Due to delays regarding the proposed new PSCN School, the numbers of students in North

Kent still requiring specialist provision at this time, and the fact that all Special Schools in the

locality are already over capacity, there is a clear need for further expansion of state-funded

specialist provision to ensure the current number of places can be maintained on a permanent

basis.             

 

This proposal is part of a plan to help alleviate current pressures and help mitigate future

population growth across the wider North Kent area, alongside the expansion of SRPs and

mainstream inclusion.

 

Options (other options considered but discarded)

 

KCC has considered whether other Special Schools in the North Kent area are viable candidates for a permanent increase to their formal designated numbers. There is also a proposal to expand Broomhill Bank School, but this alone will not produce sufficient places to meet current demand, as that expansion primarily relates to additional places for secondary age children. Therefore, Parkwood Hall Co-operative Academy is the most appropriate and viable option to also increase its designated number. It is however, recognised there is no guarantee these places will be offered to Kent children, and we have no statutory intervention powers to secure these placements. Although this has been considered an acceptable risk.

        

By increasing their formal designated number through the physical expansion of Parkwood Hall Co-operative Academy, which is a state-funded provision, it protects the Local Authority from increased revenue costs. The proposal will help to mitigate against the need to place students further away from home and incurring additional transport costs, alongside incurring increased costs from placing a greater number of children in high-cost independent settings to alleviate the current pressures in KCC state-funded Special Schools in the area.

 

How the proposed decision supports the Framing Kent's Future - Our Council Strategy 2022-2026

 

The 'Securing Kent's Future' strategy outlines the measures that KCC intend to take to ensure that Kent remains financially stable, now, and long into the future. It describes the statutory priorities.

 

This proposed decision supports Priority 1 of Framing Kent’s Future-Our Council Strategy 2022-2026:

·         Priority 1: Levelling Up Kent – It will help maintain KCC’s strategic role in supporting schools in Kent to deliver accessible, high quality education provision for all families.

 

How the proposed decision supports Securing Kent’s Future 2022-2026: Securing Kents Future - Budget Recovery Strategy.pdf

 

This proposed decision is compliant with Objective 1 of Securing Kent’s Future, KCC as the LA proposes to expand Parkwood Hall Co-operative Academy.This proposal is necessary for KCC to continue to deliver the statutory duty, in a cost-effective way, in line with the guidelines described in the Securing Kent's Future 2022-2026 strategy.

 

The proposed new Strategic Statement will be presented to Full Council on 6 November 2025 and considered for adoption. As this FED was drafted prior to that date, it aligns with the relevant policies at the time. Even though the Cabinet Committee Paper will be published after 6 November 2025 Full Council meeting, it will have been drafted prior to the adoption of a new Strategic Statement and so will also refer to Securing Kent’s Future 2022-2026.

 

Financial Implications

 

Progression of the scheme will be dependent on the outcome of detailed feasibility and design work – these will inform the full overall cost of the scheme, at which point the formal decision will be taken by the Cabinet Member for Education and Skills. The project will be a school managed scheme and will be confirmed via legally binding funding and development agreements between KCC and Parkwood Hall Co-operative Academy.

 

The cost of the works will be borne by the CYPE High Needs Capital Budget; this is funded from a ring-fenced Capital Grant from the DfE. From initial feasibility studies, the estimated cost for the whole scheme was £1,500,000. However, after initial feedback from KCC Infrastructure colleagues, there is a possibility that costs may increase, primarily due to the possible need for additional Highways mitigations around the Parkwood Hall Co-operative Academy site and other requirements on the refurbishments of existing buildings. Therefore, we will not be requesting the formal decision to be taken until such time that planning is concluded, and the full extent of the cost of the scheme is known. The latest estimates indicate the costs could increase to as much as c£3,000,000, but much work still needs to be undertaken with Planners and Highways to determine the extent of any mitigations that may be required. 

 

For Special School capital projects, the average cost per student place for a school expansion in Kent is c£85,000. However, the higher estimated cost for this scheme equates to a cost per place of only c£42,000, which demonstrates good value for money.            KCC Project Managers will be undertaking continuous checks to keep build project costs as low as possible.

 

An allowance of up to £2,500 may be payable to Parkwood Hall Co-operative Academy to outfit each new teaching room with appropriate ICT equipment, such as touch screens or projection equipment. This will be met from the overall Capital allocation for this scheme.

 

The High Needs Capital Programme has been running since 2020-21 with a total combined budget of just under £109m of which £67m has been either spent or committed to current known schemes (as at Quarter 1 2025 capital monitoring reported to Cabinet in September 2025).In the same way as the Basic Need programme is managed, to ensure all schemes are prioritised appropriately and expenditure is controlled within available funding, any proposed new or additional capital expenditure, first needs to be considered by KCC Officers through Education Asset Board, before being progressed through the formal governance processes and included in the capital programme.

 

Should the scheme not proceed through to completion, any costs incurred at the time of cessation would become abortive costs and are likely to be recharged to Revenue. This would be reported through the regular financial monitoring reports to Cabinet. This would be a cost to the General Fund.

 

State funded Special School places are commissioned by Local Authorities and paid based on a rate per place. The rate per place for Parkwood Hall Co-operative Academy is currently between £30,430 to £31,400 dependent on the Key Stage. The higher rate forParkwood Hall Co-operative Academy is approximately c£30,000 less than a place in an independent Special School. Local Authorities use the High Needs Block of the Dedicated Schools Grant to pay for these places. Parkwood Hall Co-operative Academy will use the revenue income they receive to facilitate additional staffing requirements and increased running costs.

 

Legal Implications

 

Under the Children and Families Act 2014 KCC has a duty ‘to support the child and his or her parent, or the young person, in order to facilitate the development of the child or young person and to help him or her achieve the best possible educational and other outcomes’. By ensuring we have appropriate provision as locally as possible, we are delivering on our obligation in accordance with this legislation.

 

Local Authorities need to deliver their statutory duties and be aware of non-statutory guidance and advice, which relate to children and young people with SEN. These are:

·       Department for Education-Making significant changes to an academy 2025: non-statutory guidance on collaborative school place planning and making organisational changes to academies.

·       The Equalities Act which:  places duties on Local Authorities to review support services and in doing so requires Local Authorities to have due regard to the way in which any changes will affect children and young people with a disability.

·       The SEND Code of Practice places requirements on Local Authorities to: provide access to advice from a suitably qualified person as part of the EHCP process and subsequent “assess, plan, do, review” cycles, and make appropriate provision for those with an EHC plan in the 0-25 range.

·       Sufficiency Duties: KCC is under a statutory duty to contribute towards the spiritual, moral, mental, and physical development of the community by securing that efficient primary education and secondary education are available to meet the needs of the population of their area: section 13 of the Education Act 1996 (“the 1996 Act”).

·       KCC must ensure that its education functions are exercised by the authority with a view to promoting high standards, ensuring fair access to opportunity for education and training, and promoting the fulfilment of learning potential by every person under the age of 20 and those over the age of 20 and for whom an EHC Plan is maintained: section 13A. By section 14, KCC must secure that sufficient schools for providing primary and secondary education are available for their area, defined as being sufficient in number, character and equipment to provide for all students the opportunity of appropriate education.

·       Under section 27 of the Children and Families Act 2014 (“the 2014 Act”), KCC is under a duty to keep under review the educational provision, training provision and social care provision made in its area (and outside it) for children and young people who have special educational needs or a disability. KCC must consider the extent to which its provision is sufficient to meet the educational needs, training needs and social care needs of the children and young people concerned.

·       KCC, when carrying out its functions must have “due regard” to the provisions of section 149 of the Equality Act 2010, known as the ‘public sector equality duty’.

 

Planning permission will be required for the new accommodation to enable the expansion of the school’s accommodation. As part of the Funding Agreement, Parkwood Hall Co-operative Academy will be responsible for gaining the appropriate planning consent.

 

All individual proposals to either establish new, expand current or cease current provision will be required to go through the DfE process of making significant changes to an academy (non-statutory guidance on collaborative school place planning and making organisational changes to academies, August 2025).

 

The Director of Infrastructure in consultation with the Director of Education will be overseeing the scheme to ensure public funds are utilised appropriately.

 

Decision type: Key

Decision status: For Determination

Notice of proposed decision first published: 21/10/2025

Decision due: Not before 19th Nov 2025 by Cabinet Member for Education and Skills
Reason: To allow 28 day notice period required under Executive Decision regulations

Lead member: Cabinet Member for Education and Skills

Lead director: Christine McInnes

Department: Education & Young People's Services

Contact: Ian Watts, Assistant Director Education, North Email: ian.watts@kent.gov.uk Tel: 03000 414302.

Consultees

The proposed decision will be considered at the Children’s, Young People and Education Cabinet Committee on 18 November 2025.

 

Financial implications: Please see detail above

Legal implications: Please see detail above

Equalities implications: Equalities implications Equality Impact Assessments (EqIA) have been produced by KCC and Parkwood Hall Co-operative Academy. No issues were identified in the early stage EqIAs to the proposed expansion of Parkwood Hall Co-operative Academy. The early-stage EqIAs will be reviewed as the scheme continues. The proposed expansion of Parkwood Hall Co-operative Academy will not change the delivery of education with the school. Therefore, there should be no equalities implications. Data Protection implications Any information that would have Data Protection implication was gathered by Parkwood Hall Co-operative Academy, as its own Data Controller. Any protected data will be managed by the school.