  • Decision details
  • Decision details

    21/00048 A228/B2017 and B2017/B2160 Paddock Wood Junction Improvements

    Decision Maker: Cabinet Member for Highways and Transport

    Decision status: Recommendations Approved

    Is Key decision?: Yes

    Is subject to call in?: Yes

    Purpose:

    The Cabinet Member for Highways and Transportation is asked to give approval for the County Council

    i) to progress the proposed junction improvements as indicatively shown on drawings SK24 Rev 4; and SK49 Rev D and SK50 Rev D through surveys, design and construction;
    ii) to submit the proposed junction improvements shown on drawings SK24 Rev 4; and SK49 Rev D and SK50 Rev D for Land Charge disclosures and development control;
    iii) to take a transfer of land for the B2160 junction improvements from the adjacent housing development under a S106 planning obligation and to acquire other land and rights as necessary;
    iv) to progress all statutory approvals and consents required for the scheme including detailed planning consent, drainage and environmental consents and securing temporary use of land for a construction site compound;
    v) to enter into construction contracts as necessary for the delivery of the scheme, subject to approval of the Infrastructure Commissioning Board to the recommended procurement strategy; and
    vi) for any further decisions required to allow the scheme to proceed through to delivery to be taken by the Interim/Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member.

     

    ·   Background

    Paddock Wood is a housing growth area within Tunbridge Wells Local Plan.  Three developments at Mascalls Court Farm, Mascalls Farm and Church Farm were given planning consent in 2018.  Development progress is at various stages but has started at all three sites and together they will deliver nearly 1,000 new homes.  As part of the traffic mitigation to accommodate these new developments, improvements were identified for the A228/B2017 and B22017/B2160/Mascalls Court Road junctions.

    The proposed improvement of the A228/B2017 junction is for an enlarged roundabout within the existing highway boundary to achieve  an increased diameter with wider entry lanes and more circulating space.  The proposed improvement of the B22017/B2160/Mascalls Court Road junction is to locally realign the B2170 and change the current staggered priority junction into a traffic signal-controlled crossroads together with pedestrian crossing facilities.

    As three developments are involved with no individual development willing to take overall responsibility or liability to implement the works under a S278 agreement, the former Leader of the County Council decided in 2014 that KCC would deliver the junction improvements and the S106 agreements were completed on that basis.

    The S106 agreements have intervention triggers but there was an over-riding longstop date of 1 April 2021 whereby KCC was obliged to notify the developers of its intent to progress the improvements.  That notification was issued on 29 March 2021 and that triggered the full or progressive payment of the contributions such that they will all have been received by 31 December 2021.  There is also an obligation to transfer a small area of land required for the B2017/B2160/Mascalls Court Road junction scheme.

    KCC has a ‘reasonable endeavours’ obligation to complete the improvements by 1 April 2023.  However, while Officers are proceeding diligently, surveys are required before detailed design can proceed, public engagement will be required and the B2017/B2160/Mascalls Court Road junction proposal will require planning consent and it is possible that construction may not be able to start before spring 2023.  One agreement also has an obligation to return the contribution if the improvements have not started within 5 years – April 2026 – however, the construction period is only about 9 months and so that risk is minor.

     

    ·   How the proposed decision meets the objectives of ‘Increasing Opportunities, Improving Outcomes: Kent County Council’s Strategic Statement (2015-2020)’

    The scheme supports the objectives by reducing congestion, improving the highway infrastructure to provide more reliable journey times and improved public transport links and accessibility, to support Kent business and housing growth and encourage economic activity to benefit the local and wider communities.

     

    Decision:

    As Cabinet Member for Planning, Highways, Transportation and Waste, I agree to give:

     

    i.          Approval to progress the proposed junction improvements as indicatively shown on drawings SK26 Rev P4; and SK49 Rev A and SK50 Rev B through surveys, design and construction;

    ii.         Approval for the proposed junction improvements shown on drawings SK26 Rev P4; and SK49 Rev A and SK50 Rev B to be used for Land Charge disclosures and development control;

    iii.        Approval to take a transfer of land for the improvements from an adjacent housing development under a S106 planning obligation and acquire other land and rights as necessary;

    iv.        Approval to progress all statutory approvals and consents required for the scheme including detailed planning consent, drainage and environmental consents and securing temporary use of land for a construction site compound;

    v.         Approval to enter into construction contracts as necessary for the delivery of the scheme subject to the approval of the Infrastructure Commissioning Board to the recommended procurement strategy; and

    vi.        Approval for any further decisions required to allow the scheme to proceed through to delivery to be taken by the Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member.

    Publication date: 07/07/2021

    Date of decision: 07/07/2021

    Effective from: 15/07/2021